Redevelopment of No. 70 Morris Street in Chinatown begins. 5 community organizations to be relocated in 2030

AI summary

Summary of article:

Reconstruction began at No. 70 Morris Street in Chinatown following a level five fire in 2020. It will be converted into an 8-storey community cultural centre. It is expected to be completed in 2030 and return the five institutions that were originally shifted to their original locations.

On the 9th, a groundbreaking ceremony was held for the reconstruction of 70 Mulberry St. in Manhattan’s Chinatown. The century-old building was severely damaged by a five-alarm fire in 2020, forcing the evacuation of the five community agencies within it. The reconstruction project will transform the original five-storey building into an eight-storey community cultural centre, and increase public space by approximately 30%. The project is expected to be completed in 2030, with an allocation of NT$184 million.

Number 70 Maubilly Street was built in 1892 and was originally the 23rd public school. After closing in the mid-1970s, it became the Chinatown Senior Center, United East Athletic Association, Chen Dance Center, United States.Sugar Home of the Museum of Art (MOCA) and the Chinatown Manpower Project.

On January 23, 2020, Lunar New Year’s Eve, a five-alarm fire broke out in the building and forced five agencies to evacuate. Some organizations later resumed services at temporary sites, but on a smaller scale than before.

Yume Kitasei, director of the Municipal Administrative Services Bureau, recalled the scene of residents coming here in the past to take language classes, learn dance, and have lunch with friends at the senior citizen center. She said that the fire caused Chinatown to lose an important meeting place; a few months laterpandemic Shutting down the city makes it harder for residents to live together.

The new building will retain the original two-story exterior walls and historic staircase, and will add six community rooms and a dedicated kitchen for the senior center. Paul A., director of the city’s Department of Design and Construction. Ochoa said the sixth-floor multipurpose hall will overlook Columbus Park and be connected to an outdoor terrace that will seat 475 people. The building will be designed to be completely barrier-free, and solar panels mounted on the roof and exterior walls are expected to supply up to 30% of the entire building’s electricity consumption.

The building will also feature artist Jennifer Wayne Ma’s public art work “Wings of Change.” The main part is a hanging sculpture approximately 33 feet long, consisting of objects salvaged from the scene of the fire and a glass ball used as a time capsule to preserve stories related to the building.

City Councilor Christopher Marte, State Senator Brian Kavanaugh and other civic representatives attended and gave speeches. Beiqingmeng thanked successive delegates for their support for reconstruction, and noted that former Mayor Bill de Blasio and then-City Councilor Margaret Chin had promised to invest 170 million yuan in 2021, and the city government later sought additional funds with Ma Tai.

Mayor Zohran Mamdani said in a press release that for years, it has been a place where neighbors gather, seniors make friends and cultural groups continue Chinatown traditions. After the fire, these groups and the residents who depended on their services had to find somewhere else to go. “Now, we’re getting them home.”

At the groundbreaking ceremony, dance performances were given by the Chinatown Senior Citizens Center and Chen Dance Center. (Reporter Cao Xinyuan/Photography)

A groundbreaking ceremony was held for the reconstruction of 70 Mulberry Street in Manhattan’s Chinatown, and the project is expected to be completed in 2030. (Reporter Cao Xinyuan/Photography)

Summary FAQ


  • The original 5-storey building will be converted into an 8-storey community cultural centre, with 6 new community activity rooms and a dedicated kitchen for the elderly centre. The public space will also be expanded by approximately 30% compared to the original space, and a barrier-free design will be adopted.


  • The five institutions affected include the Chinatown Senior Center, the United East Athletic Association, the Chan Dance Center, the Museum of Chinese in America, and the Chinatown Manpower Center. Some institutions have continued to provide service at temporary locations.


  • The project received an allocation of NT$184 million to preserve part of the historic façade and stairs, install solar panels on the roof and façade, and install public art works. When completed, it will recreate an important gathering and cultural service space in Chinatown.

Share on Social Media

Leave a Reply

Your email address will not be published. Required fields are marked *